Single Anchor Loading System (SAL) Logistics

When one of our neighbours in the port of Argentia was contracted to fabricate the SAL systems for Hebron, they engaged Integrated Logistics to manage the movement of those units to the load out Quay in Argentia. Due to route and existing utility considerations, the units were transported in three pieces for final assembly on the quayside. The project had two individual SAL units both measuring approx. 43 feet high and weights of 135 tonnes each. The project successfully coordinated between multiple logistics and utility partners for on time and safe delivery.

Most Recent Projects
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.